BUILD LOG · 2026-08-11 · CFC Outreach

Skyrange Nynja Kit Inspection

Inspection day! 4-5 long crates on pallets, and a box the size of a filing cabinet full of hardware, cables, and the paperwork you sign to say you've received all of it. With our BMAA-assigned inspector, Phill, Prof. Guy and some members of the team spent the morning unstrapping, cross-checking against the packing list, and tallying every sub-assembly. By the evening, the team had chalked out each sub-assembly in the inventory list and documented whether it was good to go.

Prof. Guy Gratton in front of one of the crates

This marked the first stage of BMAA-mandated inspections, ensuring that every component was accounted for and met the necessary standards before the build officially begins. With the inventory successfully verified, the team is now ready to proceed to the next phase.